伊人不卡,国产乱码一二三区精品,亚洲午夜综合,亚洲网站在线,亚洲国产二区三区,开心伊人网,tiantianri

 
 

Home/News

CGGC installs the first China-made Turbo-genrator set in TGP

Updated: 2007-06-13

On June 6, 2007, CGGC installed the first China made Turbo-generator set in TGP right power station and enter into inspection and acceptance stage, it is expected to be put into operation this June.

26# unit in TGP right plant is the first 700 MW turbo-generator set developed and installed successfully in China with introduced and digested foreign techniques, marking the world-class turbo-generator designed, manufactured and installed independently by China.

TGP Power Station is the largest one in the world with 32 of 700MW units, among which 14 at left plant, 12 at right plant and 6 at underground plant; Thus the total installed capacity will be 22400 MW. 14 units in left plant has been put into operation on Sep.16,2005, one year ahead of schedule, 12 turbo-generators in right plant was installing recently, among which 8 China made unit was contracted by CGGC .

 

Links Privacy Statement Terms of Use Contact Us

Copyright@2013 China Gezhouba (Group) Corporation. All rights reserved.