伊人不卡,国产乱码一二三区精品,亚洲午夜综合,亚洲网站在线,亚洲国产二区三区,开心伊人网,tiantianri

Global EditionASIA 中文雙語(yǔ)Fran?ais
China
Home / China / Innovation

Cold functional test starts at China's first Hualong One nuclear project

Xinhua | Updated: 2019-04-27 20:13
Share
Share - WeChat

FUZHOU -- Cold functional tests began Saturday on a reactor of China's first nuclear power project using Hualong One technology, a domestically developed third-generation reactor design.

The test was conducted on a circuit of the No. 5 nuclear power unit in the city of Fuqing, eastern China's Fujian Province, to evaluate the performance of the circuit system and its supporting facilities under high-pressure conditions, according to the China National Nuclear Corporation (CNNC).

The CNNC said the test started 50 days ahead of schedule.

Hualong One reactors were jointly designed by two nuclear power giants, China General Nuclear Power Group and the CNNC, and passed inspection by a national panel in August 2014.

China has since approved the use of Hualong One technology to build two reactors in Fujian, the No. 5 and No. 6 units.

Top
BACK TO THE TOP
English
Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US